Project Value: $100,000.00
Project Schedule: January 2010
The work for this project consisted of installation of combined SVE Air Sparge Blower System with associated Headers, Carbon Treatment of collected waters, and direct to atmosphere air venting.

The construction activities consisted of the following: 

  • Installation of a Ritchie  rotary claw blower for SVE
  • Installation of a Rotron Blower for Air Sparge 
  • On site construction of multi well header systems for both SVE and Air Sparge
  • On site construction of GAC system for treatment of waters produced by SVE System including 9 valve header to facilitate back flushing of GAC vessels and a Vacuum Breaker Loop.