Hydrotest Water Treatment

Hydrotest Water Treatment

Project Type
Project Value: $95,000.00
Project Schedule: June - July 2011

Client required on-site treatment of hydrotest water for three separate segments of pipeline.

Clean Harbors provided staffing and treatment system to treat the hydro-test water to meet discharge permits at all three sites. The treatment system was designed to treat average flow rate of 600gpm. Hydro-test water was filtered through 25um bag filters and through the mobile carbon filtration/adsorption unit prior to discharge.

The unit was mobilized to each of the three sites and operated24 hours/day, seven days per week or as dictated by the client’s schedule.

Client-Spectra Energy/Texas Eastern Pipeline

Location-Indiana/Illinois